Balochistan High Court orders comprehensive survey of illegal tubewells in Quetta

QUETTA: The Balochistan High Court has directed comprehensive measures to identify illegal tubewells in Quetta city and its surroundings, act against alleged illegal occupation of government tubewells, and improve the water supply system.
The orders were issued by a two-member bench comprising Chief Justice of the Balochistan High Court Justice Muhammad Kamran Khan Malakhail and Justice Muhammad Najmuddin Mengal, during the hearing of a constitutional petition filed regarding the water supply in Quetta.
Legal status of tubewells
During the hearing, B-WASA told the court that about 80 per cent of the B-WASA pipelines used to supply water from private tubewells in some areas of Hazara Town have been disconnected, but a comprehensive survey is needed for the remaining areas.
According to a report by the Deputy Commissioner Quetta East, only 68 of 295 tubewells hold a No Objection Certificate (NOC), while 227 tubewells are operating without an NOC.
The court observed that this report does not provide complete information on the total number of tubewells in Quetta city and its surroundings or their legal status. It therefore declared the report non-final and rejected it.
The court also rejected, as unsatisfactory, the report of the committee formed under the Secretary PHE on illegal tubewells and the minutes of the meeting held on 5 November 2026. It directed the Secretary PHE to form an effective team to conduct a fresh comprehensive survey of all tubewells in Quetta city and its surroundings and to present complete details of illegal tubewells.
The court sent the petition concerning alleged illegal occupation of government tubewells and the persons involved to the Deputy Commissioners of Quetta East and Quetta West, directing them to conduct an inquiry and submit a report at the next hearing.
Water supply situation
During the hearing, B-WASA officials said that nine tubewells around the Kharkhasa Dam are operational and are supplying water to the eastern and western areas of Hazara Town on alternate days. Arrangements are being made to convey water from four tubewells in Sajawal Abad to a three lakh gallon storage tank at the Hazara Town graveyard and other water reservoirs.
Officials said five tubewells near the Akhtarabad Dam have not yet become operational due to incomplete electricity connections, pipelines and other essential construction work.
Counsel for the petitioner argued that seven blocks of Hazara Town are receiving water, but the supply is irregular and extremely limited.
The court directed the concerned B-WASA engineer to complete essential work without delay, including urgent repair and replacement of old and dilapidated pipelines for water distribution, and to submit a progress report at the next hearing.
The court also ordered the Secretary PHE to submit a report containing a comprehensive plan for the future water supply of Quetta city and its surroundings. The court directed that a copy of the order be sent to the office of the Additional Advocate General, and adjourned further hearing of the case until 23 December 2026.